Change request implementation must be planned and scheduled carefully. It is very significant for a successful change. Also, planning and scheduling allows minimizing vital business functions disruption.

In case chosen time period overlaps another scheduled change implementation, it is recommended to minimize the effect caused to the multiple services or CI's at a time when implementing.

It is a good practice to follow the rule: One timeframe – one change request.

Change Schedule helps monitoring scheduled changes and points up conflicts (overlapping implementations).

Change Schedule interface


Change Schedule page

To check out the planned changes, navigate to Change Enablement → Change Schedule.

Change Schedule includes change request records in the following states: Authorization (approved and not defined), In Progress. Change requests in other states and requests with denied approvals will not be displayed.

Change Schedule consists of the following elements:

  1. Change Requests list – displays the title of a record and information about the assigned user and service.
  2. Timeline Scale – displays dates or dates and hours depending on the selected View Type.
  3. View Type – defines the range of time displayed. When Day is selected, then the Scale displays hours and dates. When Week is selected, the Scale displays dates without hours.
  4. Navigation – provides navigation through the timeline. Click Today to get to the current date and time.
  5. Timeline – displays the duration of a scheduled change in proportion to the Timeline Scale.

Change Schedule on a form

To open the Change Schedule, perform the following steps:

  1. Navigate to Change Enablement → All.
  2. Open the record you need or create a new one.
  3. Scroll down and open the Schedule tab, fill in the fields
  4. Click Change Schedule.

Unlike the page variant of the Change Schedule, this widget contains the following elements:

  1. Datetime fields – here you can change the schedule of the current record to control overlaps. Click Apply to update the timeline.
  2. Only Crossed Elements – select this checkbox to display only overlapping records. This overlap is shown on the timeline (3).

The current record is highlighted by blue color.