Change request implementation requests must be planned and scheduled carefully. It is very significant , which is crucial for successful change implementation. Change requests pPlanning and scheduling change requests allow for minimizing disruption to vital business functions disruption.

Tip

It is good to We recommend that you follow the rule: one timeframe – one change request.

Thus we , you make sure that changes in multiple services or CI's do not affect each other during implementation.

The Change Schedule functionality helps to monitor scheduled changes and points out conflicts between among overlapping implementations.

Info

The Change Schedule page includes change request records in the following states: Authorization (approved and not defined), In Progress, and Scheduled. There will not be displayed change Change requests in other states and requests with denied approvals are not displayed.

Change Schedule interface


In SimpleOne there There are two ways to open open Change Schedule:

Change Schedule page


To check out the planned changes, navigate to Change Enablement → Change Schedule.

Change Schedule The page consists of the following elements:

  1. Change Requests list – displays the title of a record and information about the assigned user and service. Click on the change request to open the record in a new tab.
  2. Timeline Scale – displays dates or dates and hours depending on the selected View Type.
  3. View Type – defines the range of time displayed. When Day is selected, then the Scale scale displays hours and dates. When Week is selected, the Scale scale displays dates without hours.
  4. Navigation – provides navigation through the timeline. Click Today to get to the current date and time.
  5. Timeline – displays the duration of a scheduled change in proportion to the Timeline Scale.

Change Schedule on a change request form 
Anchor
change request form
change request form


To open the Change Schedule, perform the following steps:

  1. Navigate to Change Enablement → All Change Requests.
  2. Open the change you need or create a new one.
  3. Open the Schedule tab , and fill in the fields.
  4. Click Change Schedule.

Image RemovedImage Added

Unlike thepage variant of Change Schedule, this widget contains the following elements:

  1. Datetime fields – change the schedule of the current record to control overlaps. Click Apply to display a new time interval on the timeline.
  2. Only Crossed Elements – select this checkbox to display only overlapping records. This overlap is shown on the timeline (3).

The current record is highlighted in blue color.

Note

The start and end date-times will be applied via the Change Schedule to the Planned Start Datetime and Planned End Datetime fields accordingly. You need to click Click Save or Save and Exit to apply the changes.

If the processes overlap, check information about the change requests by clicking on the titles. If the processes may affect each other and cannot be implemented at the same time, reschedule them.