A priority of the issue can be figured out based on its impact and urgency using a priority matrix.

The impact of an issue indicates the level of damage that will be caused to the business user. In SimpleOne, the impact can be categorized as:

  1. Low;
  2. Medium;
  3. High;
  4. Very High.

The urgency of an issue indicates the measure of time until an issue has an impact on the business. In SimpleOne, the urgency can be categorized as:

  1. Low;
  2. Medium;
  3. High.

Based on the priority, issues can be categorized as:

  1. Low;
  2. Moderate;
  3. High;
  4. Critical.

The priority matrix

Impact / Urgency

Very High

High

Medium

Low

High

Critical

Critical

High

Moderate

Medium

Critical

High

Moderate

Low

Low

Critical

Moderate

Low

Low

...